Application Instructions :
PERMASEAL

1. Ensure the surface of the paving is dry and that Kiln Dried Sand is used to ensure minimum moisture is present.

2. Shake the drum of PERMASEAL to ensure there is no settlement in transit.

3. Decant the PERMASEAL into a sprayer unit or clean watering can with a rose attachment.

4. Apply the PERMASEAL at a rate of 3m2/litre on block paving or flagstones. Increase application on areas with larger joints.

5. Remove any excess sealer from the surface using a flexible squeegee. Any excess will be pushed into the jointing sand.

6. The PERMASEAL will cure within 2 hours @ 20º C or slower if the temperature is lower. Avoid rain / frost during and after the application.

7. The PERMASEAL will have cured sufficiently for foot traffic after 24 hours and cars after 48 hours.


FURTHER TECHNICAL ADVICE
Should further specific technical advice be required contact the Technical Department on :-

Phone UK (01635) 202224
FAX (01635) 202230

Phone International +44(0) 1635 202224
Fax International +44(0) 1635 202230

E-mail info@picsuk.com
Web Site www.picsuk.com

 